The Secret to Canned Sardine Benefits: Why You Shouldn't Remove the Bones Global Cooperation of Autocratic Regimes: An Analysis by The Economist Russian corvette 'Mercury' damaged in Libya: potential Ukrainian link reported Carlos Alcaraz wins his first ATP Finals title House of Culture director from Obukhiv region impressed judges of 'The Voice of Ukraine-14' General Staff: Tense situation on the frontline, Kostyantynivka and Pokrovsk directions remain key hotspots Scheduled power outages in Obukhiv for November 23 Unknown assailants commit murder in Kharkiv: police operation underway Child Rescued from Rubble in Kyiv Region Following Overnight Attack Preparing for winter: how to protect your home from rodents The Secret to Canned Sardine Benefits: Why You Shouldn't Remove the Bones Global Cooperation of Autocratic Regimes: An Analysis by The Economist Russian corvette 'Mercury' damaged in Libya: potential Ukrainian link reported Carlos Alcaraz wins his first ATP Finals title House of Culture director from Obukhiv region impressed judges of 'The Voice of Ukraine-14' General Staff: Tense situation on the frontline, Kostyantynivka and Pokrovsk directions remain key hotspots Scheduled power outages in Obukhiv for November 23 Unknown assailants commit murder in Kharkiv: police operation underway Child Rescued from Rubble in Kyiv Region Following Overnight Attack Preparing for winter: how to protect your home from rodents

Paper millions: how school reconstruction in Kyiv region gets delayed and tainted contractors emerge

👥 Society 2 min read 👁 4

The reconstruction of a high school in the Myronivka community faces millions spent on paperwork and the involvement of a contractor blacklisted by the AMC.

👥Society

Key points

  • Delayed reconstruction of Myronivka Lyceum No. 3
  • Substantial spending on project documentation
  • Involvement of an Antimonopoly Committee-blacklisted contractor
  • Project estimate growth to 141 million hryvnias

The situation around Myronivka Academic Lyceum No. 3 highlights systemic issues in regional public procurement. For three years, the educational institution has remained without updated facilities, while the local budget continues allocating substantial funds for paperwork. Initially, the local humanitarian department channeled millions into drafting and adjusting project documentation, which later raised numerous questions among experts and the public.

Million-dollar expenses on paperwork and political ties

The first contracts for estimates were signed in the spring of 2023 with a company linked to former regional officials. The lion's share of this enterprise's funding came precisely from Myronivka's municipal orders. However, the developed documents did not lead to actual construction work, forcing the customer to spend additional funds on adjustments.

When the total estimated cost of the planned project grew to 141 million hryvnias, the contract was awarded to a structure previously flagged for distorting bidding results. The company's presence on the Antimonopoly Committee's lists threatens the transparency and efficiency of public resource utilization.

For residents of the Kyiv region, such cases serve as a vivid reminder of the need for strict public oversight of budget spending. Communities in the region, including Obukhiv district, regularly face challenges when social infrastructure restoration turns into protracted bureaucratic delays. Residents understand that efficient budget management is key to swift recovery without overpaying dubious contractors.

Source kyivschina24.com — kyivschina24.com/news/141-miljon-dlya-pidryadnyka-z-chornogo-spysku-amk… ↗